Yunnan construction project management approach completion and acceptance
Published on.
2013-12-19
25 March OO nine Yunnan Department of Housing and Urban No. 16 published public notice announced the " Yunnan construction project completion and acceptance management approach ."
25 March OO nine Yunnan Department of Housing and Urban No. 16 published public notice announced the " Yunnan construction project completion and acceptance management approach ."
-------------------------------------------------- ------------------------------
Accessories:
Registration Number: Yun Fu Teng No. 557
Yunnan Provincial Department of Housing and Urban-Rural Development
ANNOUNCEMENT
No. 16
" Yunnan construction project completion and acceptance management approach" has 16 January 2009 7th Yunnan Housing and Urban Construction Department of the Office of Works meeting , is hereby announced , implemented since April 1, 2009 .
March 5, 2009
Yunnan construction project management approach completion and acceptance
Chapter I General Provisions
The first construction project to unify and standardize the completion and acceptance of work to ensure construction quality , in accordance with the laws and regulations , " Construction Law ", " Construction Quality Management Regulations" , combined with our province to develop this approach .
The second administrative area of the province new construction, renovation , expansion and construction supervision and management of project completion and acceptance , the application of this approach.
The second chapter completion and acceptance of the conditions
Completion and acceptance , the third construction project construction unit shall , after obtaining urban planning, public security and fire , environmental protection, urban construction archives department issued the approval or permit the use of file organization .
After the completion and acceptance of the fourth residential project should be completed all construction contract includes engineering , including outdoor organizations .
Article completion and acceptance of construction projects should be water, electricity, gas and other ancillary works completed and tested after passing organizations .
Article VI of the construction unit in the organization of work completion and acceptance of the construction of seven days ago, the following information should be submitted to the construction quality supervision agency review :
( A ) urban planning , police and fire department issued the approval or permit the use of the file ;
( B) the contract or payment for work completed Statement submitted to the sign situation ;
(C ) construction unit project completion and acceptance of the program and the composition of the inspection team ;
(D ) assessment of project quality supervision units ;
( Five ) survey, design unit project quality inspection report ;
( Vi) construction ( including subcontractors ) units completed reports, quality control data , data security and functional testing , building energy performance test data and acceptance of assessment data ( electronic version ) ;
(Vii ) quality inspection agencies engineering quality testing report ;
(H ) Residential construction quality household acceptance conditions ;
(Ix ) construction project file early test for accreditation ;
( J) construction project completion and acceptance of the declaration ( Annex 1 )
After construction engineering quality supervision agency review of the above information should be within 3 working days of final acceptance of construction projects in the book expressly agree to declare the construction completion and acceptance of units of the organization views .
The third chapter of the organization and procedures of the final acceptance
Article VII of the final acceptance Organization
Construction project completion and acceptance by the construction unit construction organizations ( including subcontractors ) , survey , design, supervision and related organizations , such as the main responsibility for the project leader of the inspection team was established unit project quality inspection, the inspection team composed of qualified personnel shall comply with the requirements.
Article VIII acceptance of the content and procedures
Quality ( a ) acceptance control group to deal with the construction materials, safety and function test data for verification and acceptance ;
(Ii ) acceptance of the use of functional groups to deal with major construction projects carried out spot checks to confirm the quality of the building is mainly used functional status ;
(C ) Residential construction quality inspection team shall conduct random household acceptance verification ;
(Iv ) perception of quality inspection team shall inspect the construction entity to determine the perception of the quality of the construction project level ;
(E ) acceptance of the construction group to deal with a clear acceptance of the observations and conclusions .
Article IX construction engineering quality supervision agency to deal with the final acceptance inspection team organization , content, program oversight , quality control inspection team confirmed the information , data security and functional testing , quality and physical quality perception and acceptance opinion.
Article 10 When the parties involved in the project completion and acceptance of opinion can not form a consensus and acceptance should be resolved through consultation , to be unified views reorganize acceptance.
Chapter IV final acceptance
Article XI acceptance after completion of construction , the construction unit in the project should be completed within 15 days of acceptance of the building department to final acceptance authority for final acceptance procedures.
Completion and acceptance shall be completed registration procedures when handling and acceptance filing authority to submit the following information :
( A ) construction permit ;
(B ) construction design document review and approval book ( High-rise building structure seismic special review of ratification ) ;
(C ) construction unit project completion and acceptance of the report ;
(D ) survey, design unit project quality inspection report ;
(E ) supervision unit project quality assessment report ;
(Vi ) construction unit project completion report ;
Approved document ( seven ) urban planning, public security and fire departments, or permit issued documents ;
(Viii ) construction unit project quality warranty book signing ;
( Nine ) residential project " residential construction quality assurance" and " Residential Manual " ;
( Ten ) project cost management of construction projects issued by the agency record settlement price table (as required by the settlement price of the project must be filed ) ;
(Xi ) construction project file early test for accreditation ;
( Xii) other documents laws , rules and regulations that must be provided .
Article 12 Before construction projects put into use, the construction unit shall obtain construction administrative department authorities issued final acceptance of construction projects completed acceptance form ( Annex 2 ) .
Article XIII construction unit should be completed in full completion of the project file within six months after filing the acceptance test after the beginning of the urban construction archives formed submit corrective urban construction archives management.
Article XIV for construction engineering construction unit when the ownership , construction, engineering ownership for institutions should verify whether the construction project through final acceptance , not final acceptance of construction projects through , shall apply to all construction projects warrant .
Chapter V Supplementary Provisions
Article 15 These Measures by the Yunnan Provincial Department of Housing and Urban-Rural Development is responsible for interpretation .
Article 16 These Measures since April 1, 2009 implementation .